Tuesday, July 10, 2007

The Speedway track is coming along nicely...

View of the pitlane exit
Pit area being prepared before tentages are put up.
The 200 KVA generator arrived today.
View of the referee's tower from the startline.
Another view of the referee's tower.

With just under 2 weeks to go, the track is really looking good. We had the fence painted and the track surfaced rebuilt to last for 4 races before needing any grading stop. There are no longer any ruts as we thin down the top surface. The base is hard and holding well.

These pics were taken this morning showing the delivery of the 200KVA generator and the referee's tower. The catch fencing and electrical works will be completed on the week of the first race scheduled on the 21 Jul 2007.
Signages and decoratives will be up by the day before raceday.